Berkeley Lake’s saga which began in September 2009 after record-breaking rainfall damaged the city’s 65-year-old earthen dam, is nearly at an end. The repairs to the dam are almost complete except for installation of the sod that will cover the dam reported Mayor Lois Salter in her note to citizens dated Feb. 22, 2013.
“We had expected to be completely finished by now but the rains have not allowed any span of dry days sufficient for us to install the centipede sod that would protect from erosion …” she said.
She said a decision was made to temporarily cover the dam in erosion control matting until late April or May when the weather improves. The good news, is that N. Berkeley Lake Road, which had been closed since March 2012, has reopened. However, Gwinnett DOT is installing sidewalks along the road so a portion of the street may be reduced to one lane from time to time while contractors work on the walkways. That work is expected to be complete later this year. The water in the 88-acre spring-fed lake is slowly rising – when it’s full will depend a good bit on Mother Nature said Salter.
Read more on the Berkeley Lake dam repairs:
Berkeley Lake’s Damaged Dam a Major Issue This Year
Plans Nearly Complete for Berkeley Lake Dam Repairs
Berkeley Lake Dam Repairs Underway
N. Berkeley Lake Road to Close for Dam Repairs
Berkeley Lake to Receive FEMA Funds for Dam Repairs
Berkeley Lake Receives $2.6 Million FEMA Grant
By WSBTV.com News Staff November 14, 2023 at 5:52 pm EST Atlanta rapper T.I. cuts ribbon for his first affordable housing development ATLANTA — Atlanta rapper...
Another Old Fourth Ward development begins vertical climb Wingate’s Boulevard North project is reshaping majority of block MAY 28, 2024, 12:00PM JOSH GREEN Boulevard’s transformation...
Atlanta Housing Celebrates Groundbreaking of Englewood Senior New affordable housing project will house independent seniors aged 62 and older May 23, 2024 Atlanta Housing (AH)...
Groundbreaking held for Englewood senior housing project The new development is in Atlanta’s Chosewood Park neighborhood. Author: 11alive.com Published: 11:43 AM EDT May 23, 2024 Updated: 11:43 AM...
NALHFA Announces 2024 Award of Excellence Winners May 3, 2024 LAS VEGAS, NV – The National Association of Local Housing Finance Agencies (NALHFA) announced its...
Berkeley Lake Dam Repairs Near Completion
Berkeley Lake Dam Repairs Near Completion
Mother Nature has delayed some of the work on the city’s earthen dam, but N. Berkeley Lake Road is now open to traffic.
Berkeley Lake’s saga which began in September 2009 after record-breaking rainfall damaged the city’s 65-year-old earthen dam, is nearly at an end. The repairs to the dam are almost complete except for installation of the sod that will cover the dam reported Mayor Lois Salter in her note to citizens dated Feb. 22, 2013.
“We had expected to be completely finished by now but the rains have not allowed any span of dry days sufficient for us to install the centipede sod that would protect from erosion …” she said.
She said a decision was made to temporarily cover the dam in erosion control matting until late April or May when the weather improves. The good news, is that N. Berkeley Lake Road, which had been closed since March 2012, has reopened. However, Gwinnett DOT is installing sidewalks along the road so a portion of the street may be reduced to one lane from time to time while contractors work on the walkways. That work is expected to be complete later this year. The water in the 88-acre spring-fed lake is slowly rising – when it’s full will depend a good bit on Mother Nature said Salter.
Read more on the Berkeley Lake dam repairs:
Berkeley Lake’s Damaged Dam a Major Issue This Year
Plans Nearly Complete for Berkeley Lake Dam Repairs
Berkeley Lake Dam Repairs Underway
N. Berkeley Lake Road to Close for Dam Repairs
Berkeley Lake to Receive FEMA Funds for Dam Repairs
Berkeley Lake Receives $2.6 Million FEMA Grant
Source: http://peachtreecorners.patch.com/groups/editors-picks/p/berkeley-lake-dam-repairs-near-completion